Renewal of water pipes
Federal contribution
$642,285
Federal share50%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 20, 2017
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Victoriaville
- Construction start
- Apr 12, 2017(actual)
- Construction end
- Dec 13, 2017(actual)
Against the original forecast
- Construction start5 weeks earlyforecast May 15, 2017
- Construction end4 months earlyforecast Mar 31, 2018
Also in Victoriaville
- Protection and securing of the drinking water supply in the Beaudet Reservoir of the City of Victoriaville.$16.0M
- Victoriaville Performing Arts Centre$8.0M
- Upgrade of equipment of treatment of wastewater in the STEP$2.4M
- Replacement of ventilation systems serving the medical imaging sector (radiology and nuclear medicine)$1.4M
- Upgrade of the Arthabaska community center$1.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48844 in the federal list. How to read these figures.