Upgrade to drilled well water system at 163 Main Street
Federal contribution
$7,500
Federal share50%
of $15.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Corporation of the Town of Kearney
- Construction start
- Jun 23, 2017(actual)
- Construction end
- Oct 2, 2017(actual)
Against the original forecast
- Construction start7 weeks lateforecast May 7, 2017
- Construction end5 months lateforecast May 13, 2017
Also in Kearney
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48903 in the federal list. How to read these figures.