Matton Pumping Station
Federal contribution
$2.6M
$2,595,607
Federal share38%
of $6.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 27, 2017
20172018
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Trois-Rivières
- Construction start
- Aug 21, 2017(actual)
- Construction end
- Nov 30, 2018(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Sep 13, 2017
Also in Trois-Rivières
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48923 in the federal list. How to read these figures.