Berkley Road - Renewal of water, sanitary and storm water infrastructure
Federal contribution
$988,651
Federal share47%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 26, 2017
20182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Cambridge
- Construction start
- Sep 7, 2017(actual)
- Construction end
- Dec 31, 2018(actual)
Against the original forecast
- Construction start5 months lateforecast Apr 1, 2017
- Construction end9 months lateforecast Mar 31, 2018
Also in Cambridge
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48937 in the federal list. How to read these figures.