Berkley Road - Renewal of water, sanitary and storm water infrastructure

Cambridge, Ontario

completeDrinking WaterCWWF
Federal contribution
$988,651
Federal share47%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 26, 2017
20182019
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Cambridge
Construction start
Sep 7, 2017(actual)
Construction end
Dec 31, 2018(actual)

Against the original forecast

  • Construction start5 months lateforecast Apr 1, 2017
  • Construction end9 months lateforecast Mar 31, 2018