Selkirk Street - Renewal of water, sanitary and storm water infrastructure

Cambridge, Ontario

completeDrinking WaterCWWF
Federal contribution
$261,392
Federal share45%

of $580.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 26, 2017
20182019
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Cambridge
Construction start
Aug 9, 2017(actual)
Construction end
Dec 31, 2018(actual)

Against the original forecast

  • Construction start4 months lateforecast Apr 1, 2017
  • Construction end2 months lateforecast Oct 31, 2018