Selkirk Street - Renewal of water, sanitary and storm water infrastructure
Federal contribution
$261,392
Federal share45%
of $580.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 26, 2017
20182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Cambridge
- Construction start
- Aug 9, 2017(actual)
- Construction end
- Dec 31, 2018(actual)
Against the original forecast
- Construction start4 months lateforecast Apr 1, 2017
- Construction end2 months lateforecast Oct 31, 2018
Also in Cambridge
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48939 in the federal list. How to read these figures.