Back to projects

Restoration of Burnett Avenue Stormwater Management Facility

Cambridge, Ontario

completeWastewaterCWWF
Federal contribution
$536,000
Federal share50%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 19, 2017
20182019
Built

Approved 2 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Cambridge
Construction start
Feb 2, 2018(actual)
Construction end
Dec 31, 2018(actual)

Against the original forecast

  • Construction start10 months lateforecast Apr 1, 2017
  • Construction end3 months lateforecast Sep 30, 2018

Also in Cambridge

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48941 in the federal list. How to read these figures.