Stormwater Management Pond# PD33-03 Sediment Management

Whitby, Ontario

completeWastewaterCWWF
Federal contribution
$135,100
Federal share41%

of $330.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 28, 2017
2018
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Whitby
Construction start
Jul 1, 2018(actual)
Construction end
Oct 5, 2018(actual)

Against the original forecast

  • Construction start13 months lateforecast Jun 1, 2017
  • Construction end3 months earlyforecast Dec 31, 2018

Also in Whitby

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48956 in the federal list. How to read these figures.