Stormwater Management Pond# PD33-03 Sediment Management
Federal contribution
$135,100
Federal share41%
of $330.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 28, 2017
2018
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Whitby
- Construction start
- Jul 1, 2018(actual)
- Construction end
- Oct 5, 2018(actual)
Against the original forecast
- Construction start13 months lateforecast Jun 1, 2017
- Construction end3 months earlyforecast Dec 31, 2018
Also in Whitby
- Whitby Sports Complex$25.0M
- Ventilation Upgrade; Window Replacements; Exterior Door FOB Access; Water Bottle Filling and Hand Sanitizing Station; Childcare Vestibules; Plexiglass Partitions; Fencing$7.6M
- Outdoor Classrooms Replacement of Portable Classrooms$3.8M
- Waterfront Trail Redevelopment for Whitby, Ontario$2.6M
- Wireless Infrastructure Upgrade Project Group$2.6M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48956 in the federal list. How to read these figures.