Study update of storm sewer outfalls for Quality and Erosion Control Enhancement
Federal contribution
$41,823
Federal share42%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 28, 2017
20182019
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Whitby
- Construction start
- Mar 1, 2018(actual)
- Construction end
- Apr 30, 2019(actual)
Against the original forecast
- Construction start3 months lateforecast Dec 1, 2017
- Construction end7 months lateforecast Sep 30, 2018
Also in Whitby
- Whitby Sports Complex$25.0M
- Ventilation Upgrade; Window Replacements; Exterior Door FOB Access; Water Bottle Filling and Hand Sanitizing Station; Childcare Vestibules; Plexiglass Partitions; Fencing$7.6M
- Outdoor Classrooms Replacement of Portable Classrooms$3.8M
- Waterfront Trail Redevelopment for Whitby, Ontario$2.6M
- Wireless Infrastructure Upgrade Project Group$2.6M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48957 in the federal list. How to read these figures.