Stormwater Management Pond# PD02-01 Sediment Management

Whitby, Ontario

completeWastewaterCWWF
Federal contribution
$159,643
Federal share37%

of $430.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 28, 2017
20182019
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Whitby
Construction start
Jul 1, 2018(actual)
Construction end
May 30, 2019(actual)

Against the original forecast

  • Construction start13 months lateforecast Jun 1, 2017
  • Construction end7 months lateforecast Oct 31, 2018