Back to projects

Asset Condition Assessment and Develop Maintenance Strategy for Water / Wastewater Valves

Newmarket, Ontario

completeDrinking WaterCWWF
Federal contribution
$112,500
Federal share50%

of $225.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
201820192020
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Newmarket
Construction start
Jan 1, 2018(actual)
Construction end
Mar 30, 2020(actual)

Also in Newmarket