Develop and implement backflow prevention / cross connection program
Federal contribution
$50,000
Federal share50%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
201820192020
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Newmarket
- Construction start
- Oct 31, 2017(actual)
- Construction end
- Mar 31, 2020(actual)
Against the original forecast
- Construction start6 months lateforecast May 1, 2017