Residential Water Service Valve Replacement program

Newmarket, Ontario

completeDrinking WaterCWWF
Federal contribution
$80,979
Federal share40%

of $200.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 28, 2017
201820192020
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Newmarket
Construction start
Sep 15, 2017(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction start7 months lateforecast Mar 1, 2017

Also in Newmarket

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49016 in the federal list. How to read these figures.