Replacement of Heating, Ventilation and Air Conditioning (HVAC) and Boiler System - Water Treatment Plant

Prescott, Ontario

completeDrinking WaterCWWF
Federal contribution
$100,787
Federal share50%

of $202.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Prescott
Construction start
Sep 15, 2017(actual)
Construction end
Mar 31, 2018(actual)

Against the original forecast

  • Construction start8 months lateforecast Jan 1, 2017