Install a chlorine analyzer loop for proven contact time in distribution
Federal contribution
$50,000
Federal share50%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Cobalt
- Construction start
- Jan 23, 2017(actual)
- Construction end
- Sep 29, 2017(actual)
Against the original forecast
- Construction start8 weeks lateforecast Dec 1, 2016
- Construction end7 months lateforecast Mar 15, 2017
Also in Cobalt
- Energy Retrofit Municipal Buildings$31.3K
- Teck-Cominco Prospect Park Upgrades$23.9K
- Pumphouse Road Water Treatment Plant Backwash and Progress Valves replacement$20.0K
- Pumphouse Road Water Treatment Plant Chlorination system replacement$11.5K
- Cobalt Wetland Lagoon System Condition Assessment and Feasibility Study$11.3K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49091 in the federal list. How to read these figures.