Pumphouse Road Water Treatment Plant Backwash and Progress Valves replacement
Federal contribution
$20,000
Federal share50%
of $40.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
2018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Cobalt
- Construction start
- Sep 7, 2017(actual)
- Construction end
- May 10, 2018(actual)
Against the original forecast
- Construction start9 months lateforecast Dec 1, 2016
- Construction end7 weeks earlyforecast Jun 30, 2018
Also in Cobalt
- Install a chlorine analyzer loop for proven contact time in distribution$50.0K
- Energy Retrofit Municipal Buildings$31.3K
- Teck-Cominco Prospect Park Upgrades$23.9K
- Pumphouse Road Water Treatment Plant Chlorination system replacement$11.5K
- Cobalt Wetland Lagoon System Condition Assessment and Feasibility Study$11.3K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49096 in the federal list. How to read these figures.