Pumphouse Road Water Treatment Plant Chlorination system replacement

Cobalt, Ontario

completeDrinking WaterCWWF
Federal contribution
$11,500
Federal share50%

of $23.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 24, 2017
ApprovedMar 27, 2018
2018
Built

Approved 10 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Cobalt
Construction start
Dec 1, 2017(actual)
Construction end
Dec 31, 2017(actual)

Against the original forecast

  • Construction start12 months lateforecast Dec 1, 2016
  • Construction end6 months lateforecast Jul 15, 2017

Also in Cobalt

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49095 in the federal list. How to read these figures.