Replace Control Unit on Filter Sequencing System at the Water Treatment Plant

Edwardsburgh/Cardinal, Ontario

completeDrinking WaterCWWF
Federal contribution
$24,630
Federal share45%

of $55.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Construction start
Nov 1, 2017(actual)
Construction end
Apr 5, 2018(actual)

Against the original forecast

  • Construction start6 months lateforecast May 1, 2017