Water Treatment Plant Chlorination Analysis Improvements
Federal contribution
$40,658
Federal share46%
of $87.5K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 24, 2017
ApprovedFeb 28, 2018
201820192020
Built
Approved 9 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Mattawa
- Construction start
- Jun 5, 2017(actual)
- Construction end
- Mar 31, 2020(actual)
Against the original forecast
- Construction start5 weeks lateforecast May 1, 2017
- Construction end22 months lateforecast May 31, 2018
Also in Mattawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49103 in the federal list. How to read these figures.