Water Treatment Plant Chlorination Analysis Improvements

Mattawa, Ontario

completeDrinking WaterCWWF
Federal contribution
$40,658
Federal share46%

of $87.5K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 24, 2017
ApprovedFeb 28, 2018
201820192020
Built

Approved 9 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Mattawa
Construction start
Jun 5, 2017(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction start5 weeks lateforecast May 1, 2017
  • Construction end22 months lateforecast May 31, 2018