Water Storage Reservoir Upgrades including provision for Emergency Backup Power, SCADA Improvements, Replacement of Corroded Piping, Valves, and Access Hatches, and Construction of Access Road
Federal contribution
$44,113
Federal share35%
of $126.5K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 24, 2017
ApprovedFeb 28, 2018
201820192020
Built
Approved 9 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Mattawa
- Construction start
- Sep 11, 2017(actual)
- Construction end
- Mar 31, 2020(actual)
Against the original forecast
- Construction start4 months lateforecast May 1, 2017
- Construction end22 months lateforecast May 31, 2018
Also in Mattawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49104 in the federal list. How to read these figures.