Back to projects

Eight Street Storm Drainage Improvements

Bracebridge, Ontario

completeWastewaterCWWF
Federal contribution
$50,000
Federal share33%

of $150.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 16, 2017
2018
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Dec 18, 2017(actual)
Construction end
Jun 8, 2018(actual)

Against the original forecast

  • Construction start8 months lateforecast May 1, 2017
  • Construction end7 weeks earlyforecast Jul 30, 2018

Also in Bracebridge

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49105 in the federal list. How to read these figures.