Replacement of wastewater pipes
Federal contribution
$998,650
Federal share33%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 20, 2017
20172018201920202021
Built
Approved 2 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- City of Drummondville
- Construction start
- Apr 1, 2018(actual)
- Construction end
- Jan 20, 2021(actual)
Against the original forecast
- Construction start2 months earlyforecast Jun 4, 2018
- Construction end16 months lateforecast Sep 30, 2019
Also in Drummondville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49119 in the federal list. How to read these figures.