Replacement of wastewater pipes

Drummondville, Quebec

completeWastewaterSCF
Federal contribution
$998,650
Federal share33%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 20, 2017
20172018201920202021
Built

Approved 2 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Drummondville
Construction start
Apr 1, 2018(actual)
Construction end
Jan 20, 2021(actual)

Against the original forecast

  • Construction start2 months earlyforecast Jun 4, 2018
  • Construction end16 months lateforecast Sep 30, 2019