Complete replacement of failed sanitary sewer on Waubeek St.

Parry Sound, Ontario

completeWastewaterCWWF
Federal contribution
$96,976
Federal share6%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
201820192020
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Parry Sound
Construction start
May 7, 2018(actual)
Construction end
Jul 31, 2020(actual)

Against the original forecast

  • Construction start12 months lateforecast May 1, 2017
  • Construction end8 months lateforecast Nov 29, 2019