Replace and upsize all watermains on Prospect Street
Federal contribution
$96,976
Federal share17%
of $557.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
20182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Parry Sound
- Construction start
- May 7, 2018(actual)
- Construction end
- Sep 18, 2019(actual)
Against the original forecast
- Construction start12 months lateforecast May 1, 2017
Also in Parry Sound
- Highway 69 Project; Four-Lane Expansion from Highway 529 to Highway 522$120.0M
- Highway 69 Project; 4-Lane Expansion, Highway 559 Northerly$49.3M
- West Parry Sound Area Recreation and Culture Centre joint project between 7 Municipalities and 2 First Nations Communities$12.8M
- Upgrading of Parry Sound Wastewater Treatment Plant$5.3M
- Highway 518 - East of Highway 400 towards Orrville$2.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49185 in the federal list. How to read these figures.