Upgrades to the Munster Drinking Water Pumping Station

Ottawa, Ontario

completeDrinking WaterCWWF
Federal contribution
$675,000
Federal share50%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 25, 2017
20172018
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Ottawa
Construction start
Apr 1, 2016(actual)
Construction end
Jun 30, 2018(actual)

Against the original forecast

  • Construction end3 months lateforecast Mar 31, 2018