Back to projects

Lighting Fixture Upgrades at Approximately 20 Drinking Water Pumping Stations Across the City

Ottawa, Ontario

completeDrinking WaterCWWF
Federal contribution
$97,410
Federal share36%

of $270.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 25, 2017
201720182019
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Ottawa
Construction start
Feb 3, 2017(actual)
Construction end
Sep 30, 2019(actual)

Against the original forecast

  • Construction start10 months lateforecast Apr 1, 2016
  • Construction end6 months earlyforecast Mar 31, 2020

Also in Ottawa

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49204 in the federal list. How to read these figures.