Back to projects

Billings Bridge Drinking Water Pump Station Diesel System Upgrade

Ottawa, Ontario

completeDrinking WaterCWWF
Federal contribution
$360,000
Federal share50%

of $720.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 25, 2017
20182019
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Ottawa
Construction start
Aug 17, 2017(actual)
Construction end
Dec 14, 2018(actual)

Against the original forecast

  • Construction start17 months lateforecast Apr 1, 2016
  • Construction end5 months lateforecast Jul 15, 2018

Also in Ottawa

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49205 in the federal list. How to read these figures.