Billings Bridge Drinking Water Pump Station Diesel System Upgrade
Federal contribution
$360,000
Federal share50%
of $720.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 25, 2017
20182019
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Aug 17, 2017(actual)
- Construction end
- Dec 14, 2018(actual)
Against the original forecast
- Construction start17 months lateforecast Apr 1, 2016
- Construction end5 months lateforecast Jul 15, 2018
Also in Ottawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49205 in the federal list. How to read these figures.