Design and Installation of Inlet Control Devices in Bilberry/Chatelaine, Bridlewood North and Craig Henry (Storm water linear assets, appurtenances)
Federal contribution
$879,132
Federal share39%
of $2.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 25, 2017
20182019
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Mar 17, 2017(actual)
- Construction end
- Oct 12, 2019(actual)
Against the original forecast
- Construction start11 months lateforecast Apr 1, 2016
- Construction end24 months earlyforecast Sep 30, 2021
Also in Ottawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49206 in the federal list. How to read these figures.