Design and Installation of Inlet Control Devices in Bilberry/Chatelaine, Bridlewood North and Craig Henry (Storm water linear assets, appurtenances)

Ottawa, Ontario

completeWastewaterCWWF
Federal contribution
$879,132
Federal share39%

of $2.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 25, 2017
20182019
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Ottawa
Construction start
Mar 17, 2017(actual)
Construction end
Oct 12, 2019(actual)

Against the original forecast

  • Construction start11 months lateforecast Apr 1, 2016
  • Construction end24 months earlyforecast Sep 30, 2021