Design for Lemieux Island Water Purification Plant Intake Improvements
Federal contribution
$875,000
Federal share50%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 25, 2017
201820192020
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Aug 30, 2017(actual)
- Construction end
- Mar 31, 2020(actual)
Against the original forecast
- Construction start17 months lateforecast Apr 1, 2016
- Construction end18 months earlyforecast Sep 30, 2021
Also in Ottawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49209 in the federal list. How to read these figures.