Back to projects

Design and Construction of the Bridlewood Neighborhood Localised Flood Protection Improvement Including New Manholes

Ottawa, Ontario

completeWastewaterCWWF
Federal contribution
$787,500
Federal share50%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 23, 2017
ApprovedMar 27, 2018
20182019
Built

Approved 10 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Ottawa
Construction start
Apr 18, 2017(actual)
Construction end
Aug 30, 2019(actual)

Against the original forecast

  • Construction start13 months lateforecast Apr 1, 2016

Also in Ottawa

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49219 in the federal list. How to read these figures.