Preliminary Design for the Convent Glen North Storm Sewer
Federal contribution
$452,240
Federal share45%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 23, 2017
ApprovedMar 27, 2018
201820192020
Built
Approved 10 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Jul 17, 2017(actual)
- Construction end
- Dec 31, 2019(actual)
Against the original forecast
- Construction start16 months lateforecast Apr 1, 2016
- Construction end2 months lateforecast Oct 31, 2019
Also in Ottawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49221 in the federal list. How to read these figures.