Back to projects

Design and Construction of the Craig Henry Neighborhood Flood Protection Improvements Including Re-profiling and Storm Pipe Upsizing

Ottawa, Ontario

completeWastewaterCWWF
Federal contribution
$1.4M
$1,440,000
Federal share50%

of $2.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 25, 2017
201820192020
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Ottawa
Construction start
Apr 18, 2017(actual)
Construction end
Dec 30, 2019(actual)

Against the original forecast

  • Construction start13 months lateforecast Apr 1, 2016
  • Construction end4 months lateforecast Aug 30, 2019

Also in Ottawa

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49222 in the federal list. How to read these figures.