Design and Construction of the Craig Henry Neighborhood Flood Protection Improvements Including Re-profiling and Storm Pipe Upsizing
Federal contribution
$1.4M
$1,440,000
Federal share50%
of $2.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 25, 2017
201820192020
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Apr 18, 2017(actual)
- Construction end
- Dec 30, 2019(actual)
Against the original forecast
- Construction start13 months lateforecast Apr 1, 2016
- Construction end4 months lateforecast Aug 30, 2019
Also in Ottawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49222 in the federal list. How to read these figures.