Preliminary Design of Queensway Terrace North Stormwater Trunk Rehabilitation

Ottawa, Ontario

completeWastewaterCWWF
Federal contribution
$175,870
Federal share34%

of $520.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 23, 2017
ApprovedMar 27, 2018
2018
Built

Approved 10 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Ottawa
Construction start
May 18, 2017(actual)
Construction end
Apr 20, 2018(actual)

Against the original forecast

  • Construction start14 months lateforecast Apr 1, 2016

Also in Ottawa

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49225 in the federal list. How to read these figures.