Rehabilitation of the Didsbury stormwater facility structures and sediment removal

Ottawa, Ontario

completeWastewaterCWWF
Federal contribution
$45,000
Federal share50%

of $90.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Ottawa
Construction start
Feb 16, 2017(actual)
Construction end
Oct 31, 2017(actual)

Against the original forecast

  • Construction start11 months lateforecast Apr 1, 2016
  • Construction end5 months earlyforecast Mar 31, 2018

Also in Ottawa