Thompson - Transit Signage
Federal contribution
$4,620
Federal share46%
of $10.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
20182019
Built
Approved 5 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Thompson
- Construction start
- Jul 31, 2019(actual)
- Construction end
- Aug 16, 2019(actual)
Against the original forecast
- Construction start15 months lateforecast May 1, 2018
- Construction end11 months lateforecast Aug 31, 2018
Also in Thompson
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49270 in the federal list. How to read these figures.