Thompson - Two Transit Bus Shelters

Thompson, Manitoba

completePublic TransitPTIF
Federal contribution
$10,000
Federal share50%

of $20.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
20182019
Built

Approved 5 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Thompson
Construction start
Jun 15, 2018(actual)
Construction end
Mar 15, 2019(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 15, 2018
  • Construction end5 months lateforecast Sep 30, 2018