Construction of Maplehurst Avenue Watermain Renewal
Federal contribution
$384,904
Federal share49%
of $780.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 25, 2017
ApprovedMar 27, 2018
20172018
Built
Approved 8 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Jul 5, 2016(actual)
- Construction end
- Jun 30, 2018(actual)
Against the original forecast
- Construction start3 months lateforecast Apr 1, 2016
- Construction end3 months lateforecast Mar 31, 2018
Also in Ottawa