Water Treatment Plant Upgrade: Planning and Design
Federal contribution
$1.6M
$1,619,130
Federal share50%
of $3.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 18, 2017
201720182019202020212022
Built
Approved 8 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Brandon
- Construction start
- Dec 6, 2017(actual)
- Construction end
- Aug 9, 2022(actual)
Against the original forecast
- Construction end7 months lateforecast Dec 31, 2021
Also in Brandon
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49282 in the federal list. How to read these figures.