Transcona Sewer Relief

Winnipeg, Manitoba

completeWastewaterCWWF
Federal contribution
$1.4M
$1,401,400
Federal share47%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
2018
Built

Approved 4 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Winnipeg
Construction start
Feb 6, 2018(actual)
Construction end
Sep 30, 2018(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jan 15, 2018

Also in Winnipeg

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49318 in the federal list. How to read these figures.