City of Kenora Construction of New Bus Shelters - 5 Locations

Kenora, Ontario

completePublic TransitPTIF
Federal contribution
$52,988
Federal share42%

of $125.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 12, 2017
Built

Approved 6 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Kenora
Construction start
Sep 11, 2017(actual)
Construction end
Nov 30, 2017(actual)

Against the original forecast

  • Construction start4 months lateforecast May 23, 2017
  • Construction end3 weeks lateforecast Nov 10, 2017