Schedule

Announced and approvedMay 23, 2017
201820192020
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Caledon
Construction start
Apr 1, 2018(actual)
Construction end
Mar 31, 2020(actual)