Back to projects

Cornwall Wellfield Exploration

Cornwall, Prince Edward Island

completeDrinking WaterCWWF
Federal contribution
$184,816
Federal share45%

of $409.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 9, 2017
201820192020
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Cornwall
Construction start
Oct 1, 2017(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction end12 months lateforecast Mar 31, 2019

Also in Cornwall