Back to projects

St. Lawrence Avenue Sewer Separation and Watermain Replacement

Niagara Falls, Ontario

completeWastewaterCWWF
Federal contribution
$1.0M
$1,006,460
Federal share44%

of $2.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
201820192020
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Niagara Falls
Construction start
Dec 4, 2017(actual)
Construction end
Jul 15, 2020(actual)

Against the original forecast

  • Construction start8 months lateforecast Apr 15, 2017
  • Construction end15 months earlyforecast Sep 30, 2021

Also in Niagara Falls

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49578 in the federal list. How to read these figures.