Schedule

Announced and approvedMay 24, 2017
201820192020
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Niagara Falls
Construction start
Dec 4, 2017(actual)
Construction end
Jun 30, 2020(actual)

Against the original forecast

  • Construction start8 months lateforecast Apr 15, 2017
  • Construction end15 months earlyforecast Sep 30, 2021