Back to projects

The rehabilitation of town wells #3 & #4 located at 41A Ohsweken Road

Manitouwadge, Ontario

completeDrinking WaterCWWF
Federal contribution
$42,500
Federal share50%

of $85.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of Manitouwadge
Construction start
Aug 1, 2017(actual)
Construction end
Jun 1, 2018(actual)

Against the original forecast

  • Construction start3 months lateforecast May 1, 2017

Also in Manitouwadge

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49589 in the federal list. How to read these figures.