Replacement of 150m of Eleanor Street Watermain - From Phipps Street to Laird Street
Federal contribution
$106,066
Federal share39%
of $270.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
2018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Gore Bay
- Construction start
- Jun 27, 2017(actual)
- Construction end
- Jul 20, 2018(actual)
Against the original forecast
- Construction start3 months lateforecast Apr 3, 2017
- Construction end2 weeks lateforecast Jul 6, 2018
Also in Gore Bay