Installation of New 15 Horsepower Primary Well Pump
Federal contribution
$6,100
Federal share50%
of $12.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
20182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Hilton Beach
- Construction start
- Nov 1, 2017(actual)
- Construction end
- Sep 30, 2019(actual)
Against the original forecast
- Construction start4 months lateforecast Jul 1, 2017
- Construction end14 months lateforecast Jul 31, 2018
Also in Hilton Beach
- Upgrades to Municipal Buildings$79.9K
- Hilton Beach Community Centre Rehabilitation$51.1K
- Blower, rotating biological contactor Pump and Lift Station Pump installation$22.5K
- Upgrade Wastewater Plant$12.5K
- Upgrades to components of the Supervisory Control and Data Acquisition (SCADA) at the Wastewater Plant$9.6K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49599 in the federal list. How to read these figures.