Back to projects

Major Repairs to the Town of Shelburne Elevated Water Storage Tower

Shelburne, Ontario

completeDrinking WaterCWWF
Federal contribution
$116,113
Federal share49%

of $236.9K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 16, 2017
ApprovedMar 27, 2018
2018
Built

Approved 9 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Shelburne
Construction start
Apr 1, 2017(actual)
Construction end
Sep 30, 2018(actual)

Against the original forecast

  • Construction end6 months lateforecast Mar 31, 2018

Also in Shelburne

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49652 in the federal list. How to read these figures.