Major Repairs to the Town of Shelburne Elevated Water Storage Tower
Federal contribution
$116,113
Federal share49%
of $236.9K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 16, 2017
ApprovedMar 27, 2018
2018
Built
Approved 9 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Shelburne
- Construction start
- Apr 1, 2017(actual)
- Construction end
- Sep 30, 2018(actual)
Against the original forecast
- Construction end6 months lateforecast Mar 31, 2018
Also in Shelburne
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49652 in the federal list. How to read these figures.