Design and Construction of a new Biosolids storage facility to comply with Ministry of Environment and Climate Change guidelines
Federal contribution
$267,790
Federal share21%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 16, 2017
2018
Built
Approved 4 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Hanover
- Construction start
- Mar 15, 2017(actual)
- Construction end
- Nov 22, 2018(actual)
Against the original forecast
- Construction start5 months lateforecast Oct 1, 2016
- Construction end5 months lateforecast Jun 30, 2018
Also in Hanover