Replacement of well pump # 1 Alpine water treatment plant

Trent Lakes, Ontario

completeDrinking WaterCWWF
Federal contribution
$1,485
Federal share50%

of $3.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Municipality of Trent Lakes
Construction start
Jan 1, 2018(actual)
Construction end
Mar 5, 2018(actual)

Against the original forecast

  • Construction start7 months lateforecast Jun 1, 2017
  • Construction end5 months lateforecast Sep 30, 2017

Also in Trent Lakes

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49692 in the federal list. How to read these figures.