Point Ellice Bridge Upgrade
Federal contribution
$1.2M
$1,207,333
Federal share33%
of $3.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 11, 2017
201820192020
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- The City of Victoria
- Construction start
- May 21, 2019(actual)
- Construction end
- Jan 31, 2020(actual)
Against the original forecast
- Construction start3 months lateforecast Mar 4, 2019
- Construction end2 months lateforecast Nov 29, 2019
Also in Victoria
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49739 in the federal list. How to read these figures.